15. June 2016

Subsea Repair Clamp successfully installed

Subsea repair clamps successfully installed at the Bonga field outside west Africa.

The client is Shell Nigeria.

The repair clamps were installed at approx. 1100m water depth on water injection lines close to subsea structures. Tests after installation have been performed and shows no leaks. Design of the clamps is based on the “patch repair clamp concept” and this project proves again the capability of this concept.

The projects have been executed based on a emergency delivery of 4 weeks. During this period IK-Norway performed the custom made design, engineering, fabrication, coating, assembly and testing.